Third Runway, Cairo International Airport
Works on this project encompassed:
Stage 1: Studies
- Data collection
- Cost estimate
- Geotechnical survey
Stage 2: Preliminary design
- Coordination
- Preliminary design of:
- All aeronautical areas (runway, taxiways) including pavement and strip layout and levelling
- All service roads and security fences
- Drainage of the whole new platform and pavements
- Cable ducts and electrical manholes